New Tindo Solar Factory Construction

The new $6 million Tindo Solar factory is under construction with estimated completion by early 2021. This new facility will greatly increase our manufacturing capacity, bringing more Australian Made panels to Australians and increase exports of our proudly Australian product.

Week 13

Less work completed due to the rain this week, continued getting ready for laying the slab for the factory and warehouse.

Week 12

Exciting week with the slab for the offices poured.

Week 11

Continued with services and prepared the formwork for the office slab.

Week 10

The Footings for the office were continued and plumbing and services are going in.

Week 9

The footings for the new Tindo factory were finished and footings for the offices were poured.

Week 8

During this week the storm water detention tank was finished and the footings for the new Tindo factory were dug and poured.

Week 7

The storm water detention tank was installed and work on the footings continued for the new Tindo manufacturing facility.

Week 6

Work in progress on the footings for the new Tindo Solar manufacturing facility.

Week 5

During this week we saw the digging and pouring of concrete for the first footings.

Week 4

Preparation of the land still going according to schedule despite the welcomed rains.

Week 3

More preparation and levelling of the ground for the new Tindo Solar manufacturing facility.

Week 2

Preparing the land for the new Tindo Solar manufacturing facility.

Week 1

Building of the new Tindo Solar factory has started!

Learn More About Australian Made Solar